Surgery & PACU Expansion
The St. Vincent Surgery improvements project includes two state of the art Cardiac Surgical Suites. A Neurosurgical Suite, a 17 bed Recovery Room, significant HVAC and infrastructure upgrades and numerous small support upgrades. This project was built in two concurrent phases so that it could be accomplished in a minimal amount of time. Each phase of the project was ultimately designed, reviewed and approved, constructed, licensed and occupied in 9 and 11 months. Under a normally aggressive schedule it should have taken 24 months.
Project Objectives: